Using Pallet Jack Resource

Loading video please wait.
From the Component Library load an Energy Meter and a switch. Set the start time in the switch to 00:00:00 and the end time to 24:00:00.

From the Inline category load a “Basic Feeder” and Conveyor component.

Load the resource manager component.

Load a Pathway component and then use the interact function to stretch the pathway. Ensure the pathway connects the “Basic Feeder” and the conveyor.

Load an InLet component and PnP to the “Basic Feeder”, then load an Outlet component and PnP to the conveyor component.

Load the “Pallet Jack” component and place the component on top of the pathway.

Load the Anna component from the Resources category and place on top of the pathway.

Select the InLet component; on the Param tab set the parameter “Operator” to “Anna”, enable the parameter “Use Trolley” and set the parameter “Trolley” to the name of the pallet jack “Pallet Jack”.

Run the simulation, Anna will grab the Pallet Jack and then transport dynamic components from the “Basic Feeder” to the conveyor.


Tags

resource, manager, using, pallet, jack, palletjack, resource, operator, trolley